Prime Minister Shehbaz Sharif Sunday visited sites of different development projects in Lahore and ordered early completion of work om these projects.
Shehbaz Sharif inspected the under-construction Lahore bridge and CBD underpass to review the pace of work and directed for fast-paced completion.
During his visit to the construction site of Lahore bridge, the prime minister was apprised that the Lahore Development Authority (LDA) project worth Rs1,712 million was started in the year 2021, but delayed for two years due to the issuance of no objection certificate.
Shehbaz Sharif expressed his displeasure over the pace of work and the shutdown programme by the LESCO. He directed for initiation of legal action against the official concerned for the delay and desired completion of the process in two weeks.